what is your team velocity
Velocity is one of the planning tool used to estimate the speed of the work and time of completion of the project. • The calculation of velocity is done by reviewing the work team has successfully completed during earlier sprints; • for example, if the team completed 5 stories during a two-week sprint and each story was worth 3 story points, then the team's velocity is 15 story points per sprint.