Answers for "The Schedule Performance Index is equal to: Question 30 options: CV/PV EV/CV EV/PV AC/PV"

0

The Schedule Performance Index is equal to: Question 30 options: CV/PV EV/CV EV/PV AC/PV

Schedule Performance Index (SPI) calculation: SPI = EV/PV
Posted by: Guest on December-08-2019